Environmental risk assessment of Kermanshah petrochemical complex using FMEA method

Message:
Article Type:
Research/Original Article (دارای رتبه معتبر)
Abstract:
Introduction
Development of various industries, despite providing human welfare, has potential risks for mankind. Due to its extensive operations and activity and also the potential risk for humans and the environment, the petrochemical industry is considered a high-risk industry. The purpose of this study was to assess and prioritize the risks resulting from process activities in Kermanshah petrochemical complex using two approaches (i.e., the traditional and fuzzy FMEA method). Material and methods: The present study was an analytical-field research that has been conducted in Kermanshah petrochemical complex for 10 months. In this study, the product lines (urea and ammonia) were investigated and also a team of five experts was formed. In addition, an initial list of the most important risks and hazards in the environmental field was prepared and then, by using Brainstorming and Delphi Technique, the list was corrected. Finally, environmental risk assessment in the form of traditional and fuzzy FMEA methods was evaluated.
Results and discussion
According to the results, 38 risks were identified by traditional FMEA. The highest priority risk was related to hydrogen and ammonia gas emissions when the ammonia unit was out of service by RPN number of 491. The lowest priority risk belonged to ammonia effluents by RPN number of 28. Also, the highest risks to air pollution, as well as the causes of the risks were related to defects in the system and connections. The results of input fuzzification and output FMEA method showed that among the 15 identified risks in the petrochemical complex, the highest number of fuzzy priority in the health section was related to noise pollution (0.75), in the safety section was falling from the heights (0.75), and in the environmental sector for the reduction of ecological resources (0.613).
Conclusion
Comparing these two approaches suggest that the traditional FMEA is powerful in the early stages of risk assessment process, and on the other hand, the fuzzy approach is more flexible and user-friendly in the stage of prioritizing the risks.
Language:
Persian
Published:
Environmental Sciences, Volume:16 Issue: 3, 2018
Pages:
1 to 24
magiran.com/p1919695  
دانلود و مطالعه متن این مقاله با یکی از روشهای زیر امکان پذیر است:
اشتراک شخصی
با عضویت و پرداخت آنلاین حق اشتراک یک‌ساله به مبلغ 1,390,000ريال می‌توانید 70 عنوان مطلب دانلود کنید!
اشتراک سازمانی
به کتابخانه دانشگاه یا محل کار خود پیشنهاد کنید تا اشتراک سازمانی این پایگاه را برای دسترسی نامحدود همه کاربران به متن مطالب تهیه نمایند!
توجه!
  • حق عضویت دریافتی صرف حمایت از نشریات عضو و نگهداری، تکمیل و توسعه مگیران می‌شود.
  • پرداخت حق اشتراک و دانلود مقالات اجازه بازنشر آن در سایر رسانه‌های چاپی و دیجیتال را به کاربر نمی‌دهد.
In order to view content subscription is required

Personal subscription
Subscribe magiran.com for 70 € euros via PayPal and download 70 articles during a year.
Organization subscription
Please contact us to subscribe your university or library for unlimited access!